Answer:
Void
Explanation:
Void is the term of law, which is defined as the contract is not valid currently, and the parties of the contract are not held to its terms. The void contract is the one which is generally unenforceable.
The contract could be void because of many reasons like the contract need one party to perform that act which is impossible or in that case, where one party is not mentally incompetent.
So, in this case, the contract is most likely to be void as the contract with the party who is mentally incompetent, though the party has not been adjudged through court.
Answer:
$1,642.83
Explanation:
The amount after four years can be calculated using the formula below
A = P(1 +r)^n
where A= amount
P = Principal amount $1500
r= interest 2.3% or 0.023
n = time in year; 4
A = $1500(1 + 0.023)^4
A= $1500(1.023)^4
A=$1500x 1.095222
A=$1,642.83
Answer:
59,700 units
Explanation:
The computation of the equivalent units for the conversion cost is shown below:
= Opening work in process units × completion percentage + units started and completed × completion percentage + ending work in process units × completion percentage
= 4,600 units × 100% + 36,500 units × 100% + 31,000 units × 60%
= 4,600 units + 36,500 units + 18,600 units
= 59,700 units
Answer:
$7.50 per unit
Explanation:
Cost of buying from outside supplier = $33 per unit.
Relevant cost of making such component in-house = Direct materials+ Direct labor+ Variable overhead
= $9.50 per unit + $13.50 per unit + $2.50 per unit
= $25.50 per unit
Net incremental cost of buying the component = Cost of buying from outside supplier- Relevant cost of making such component in-house
= $33.00 per unit - $25.50 per unit
= $7.50 per unit
1=A
2=D
3=C
4=A
5=C
6=C
7=D
8=A
9=C
10=D
11=C
12=A
13=C
14=B