Answer:
$2,400 U
Explanation:
Labor efficiency variance is a financial metric that assesses a company’s ability to efficiently use labor per the expectations. The variance is worked out as the difference between the actual labor hours utilized and the standard amount that ought to have been used, multiplied by the standard labor rate.
In Clark Manufacturing:
It is given that:
Number of hours required to produce one product = 2 hours
Standard Labor rate(SLR) per hour = $12
Actual Labor rate(ALR) per hour = $12.20
Units of products produced = 2000
Number of hours required(SLH) to produce 2000 units = 4,000 hours
Actual Labor Hours(ALH) used =4,200 hours
Labor Efficiency Variance =(ALH - SLH) *SLR
= (4200-4000) *12
200*12 = $2,400 U
U means unfavorable. This variance is unfavorable because the labor cost exceeded the standard or budgeted labor cost.
Answer:
$65,000
Explanation:
Borasco was the person who purchased the land for $65,000 in which the land was later transferred to Alvo. Therefore no gain or loss is been recognized in this liquidation because it subsidiary is been liquidated by the parent which is why the basis of land is said to be carryover basis of $65,000 at the end of the transaction.
Protect them from electric shock
hope this helpss
Answer:
the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively
Explanation:
The computation is shown below:
Cost assign to units transferred out is
= 40,200 units × $4 + 40,200 units × $10
= $160,800 + $402,000
= $562,800
And, the Cost assign to work in progress is
= 6,220 units × $4 + (6,220 units × 0.40) × $10
= $24,880 + $24,880
= $49,760
Hence, the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively