Answer:$0.55
Step-by-step explanation:
The expected duration of the activity is 29 days and 4 hours.
Step-by-step explanation:
Step 1:
The optimistic time,
= 25 days,
The most likely estimate,
= 29 days.
The pessimistic time,
= 34 days.
According to PERT, the expected duration of the activity, 
Step 2:
By substituting the given values, we get
0.1666 days = 
29.1666 days approximately equal 29 days and 4 hours.
<span>None of the above. The mass does not change if you change the gravitational constant (moving to Jupiter or Moon), only the weight changes. By cutting it in half you decrease the mass, you do not increase it.</span>
Answer:
the interest for 100 in 5 years us 12.5
13 - 7 = 6,what does the make a 10 part mean?