See the picture attached to better understand the problem
we know that
in the right triangle ABC
tan 64°=AB/AC------> AB=AC*tan 64°-----> AB=x*tan 64°---> equation 1
in the right triangle ABD
tan 43°=AB/DA----> AB=DA*tan 43°---> AB=(240+x)*tan 43°---> equation 2
equate equation 1 and equation 2
x*tan 64°-=(240+x)*tan 43°---->x*tan 64=240*tan 43+x*tan 43
x*[tan 64-tan 43]=240*tan 43-----> x=240*tan 43/[tan 64-tan 43]
x=200.22 ft
AB=x*tan 64----> AB=200.22*tan 64-----> AB=410.51 ft
the answer is410.51 ft
This is the answer of this question
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.