B accepting advice as a entrepreneur really helps as and accepting advice is part of being a good leader!
Answer: 15,000 units
Explanation:
The annual output that would make them indifferent is the one that would equate both costs.
Assume that output is x.
80,000 + 20x = 140,000 + 16x
20x - 16x = 140,000 - 80,000
4x = 60,000
x = 60,000/4
x = 15,000 units
Answer:
The recording label should increase the production and distribution of Here band
Explanation:
In the given question it is stated that the Music stores can markup to the price of $17.99 with continued strong sales against the listed price of $14.99.
Now,
The markup price is the extra amount that is over the cost of product or the service.
Thus,
Here, the Markup will further increase the profit by $17.99 - $14.99 = $3
Hence,
The recording label should increase the production and distribution of Here band
Answer:
Predetermined manufacturing overhead rate= $14.77 per direct labor hour
Explanation:
Giving the following information:
Estimated overhead cost for the period= $325,000
Estimated total direct labor hours for the period= 22,000
<u>To calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 325,000 / 22,000
Predetermined manufacturing overhead rate= $14.77 per direct labor hour
Answer:
The project Charter.
Explanation:
A project charter is a structured, generally short documents that outlines the project as a whole — including what the goals are, how it will be implemented, and who are the stakeholders. It is a crucial ingredient of project planning, since it is used throughout the life cycle of the project.