Answer:
A. III only
Explanation:
One of the very useful tools in project management analysis is the PERT and CPM.
PERT (Program evaluation and review technique) provides valuable information regarding which activities need to be closely watched.
While CPM (Critical Path Method) helps in determining the time required to complete each task, and the minimum time required to complete a project.
Both CPM and PERT serve similar purposes by helping to determine projects or activities that need to be watched closely.
The filter that can be used to find a specific project when in the work area is: Project name.
<h3>Project Filter</h3>
When looking or searching for a particular project that meet your requirement in a work area, in order to find the project the best thing to do is to include the following filter as it will enables you to find the project you are looking for;
- Project name
- Due date
- Template name
- Team member
Therefore the filter that can be used to find a specific project when in the work area is: Project name.
Learn more about project filter here:brainly.com/question/23643337
#SPJ11
Answer:
The correct answer is C) behavioral barrier.
Explanation:
Organizational barriers can be any number of things that range from physical elements to individual and group attitudes. They don't have to be important elements. They can be as simple as an extended absence of employees or as important as the acquisition of an organization by a foreign government. They can even be perceptions that have no basis in reality. The key to identifying barriers and eliminating their constrictive effect is to carefully identify all aspects of them.
$8,000,000 - corporate issued
5 % - annual interest
30 % - income tax rate
Annual net cash cost - ?
Formula and Solution - (8,000,000 x 0.05) x 0.7 = 280,000
Answer: The Annual net cash cost - $280,00
Answer:
True
Explanation:
If the managers fails to pay attention, the organization cannot be successful