Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
My name is Chris I'm sorry for being so late but no I got it and I will be there for being such a great time with you and your team and I will get back to you are you still looking I'm sorry for being a little bump it to the only thing I can think of is that a little bit of time
Answer:
A = 120
B = 40
C = 70
Solution:
As per the question:
Manufacturer forced to make 10 more type C clamps than the total of A and b:
10 + A + B = C (1)
Also, 3 times as many type B as type A clamps are:
A = 3B (2)
The total no. of clamps produced per day:
A + B + C = 330 (3)
The no. of each type manufactured per day:
Now, from eqn (1), and (3):
A + B + 10 + A + B = 330
2A + 2B = 320
A + B = 160 (4)
Now, from eqn (2) and (4):
3B + B = 160
B = 40
Since, A = 3B
A = 
A = 120
Put the values of A and C in eqn (3):
120 + 40 + C = 330
C = 70
Answer:
In a series connection, the current is the same through each component regardless of any kind of components are used or their values. The voltage drops across each component in the circuit are dependent upon the values of the components used in the circuit. Another way to view a series connection is that the positive end of each component is connected to the negative end of the previous component in a 'one after the other' arrangement. The negative end of each component is also connected to the positive end of the next component.
It is one of which every component is arranged in a series connection. Hence series circuit will have same current at all points of the circuit. The voltage drop across each component in the circuit adds up to sum of voltage source across each component and of an equivalent component value. Breaking of the series circuit will make entire circuit to stop working. Suppose consider the three bulbs are connected in series connection and if even one bulb burns out or broken then all the three bulbs will stop working as well. In series circuit components like current (I) is sum of all the element and Voltage is sum of all the voltage drops and resistance is the sum of individual resistances.
Explanation: