From the question; in regard with the material requirements plan MRP for the item Z; we have the following constructed table:
Item Z 1 2 3 4 5 6 7
Gross 120
<u>Requirement </u>
<u>On-hand = 40 </u>
<u> Schedule reciept </u>
<u>Balance 40 40 40 40 40 40 - </u>
<u>Net requirement 80 </u>
Planned Order
<u>Receipt 80 </u>
Planned Order
<u>Release 80 </u>
Following the material requirements plan (MPR) for A.
Item A 1 2 3 4 5 6 7
Gross 160
<u>Requirement </u>
<u>On-hand = 70 </u>
<u> Schedule reciept </u>
<u>Balance 70 70 70 70 </u>
<u>Net requirement 80 </u>
Planned Order
<u>Receipt 90 </u>
Planned Order
<u>Release 90 </u>
Following the material requirements plan (MPR) for B.
Item B 1 2 3 4 5 6 7
Gross 320
<u>Requirement </u>
<u>On-hand = 100 </u>
<u> Schedule reciept </u>
<u>Balance 100 100 100 100 </u>
<u>Net requirement 220 </u>
Planned Order
<u>Receipt 220 </u>
Planned Order
<u>Release 220 </u>
Following the material requirements plan (MPR) for component C; we have:
Item C 1 2 3 4 5 6 7
Gross 440 270
<u>Requirement </u>
<u>On-hand = 30 </u>
<u> Schedule reciept 20 </u>
<u>Balance 50 50 </u>
<u>Net requirement 390 270 </u>
Planned Order
<u>Receipt 390 270 </u>
Planned Order
<u>Release 390 270 </u>