A market index is a resulting value created from the combination of several stocks and other investment vehicles presenting its total value against a base value at a certain period. It is used to show the whole stock market at the same time keeping track with the way the market changes overtime. The practice of tracking the value of the stock market over a period of time can be used to benchmark to make a credible comparison of stock returns.
Answer:
company B's cost of equity is 14.0375% - 8.975% = 5.0625% higher than company A's cost of equity
Explanation:
cost of equity = risk free rate + (beta x market premium)
risk free rate = 4.25%
market premium = market return - risk free rate = 11% - 4.25% = 6.75%
Company A's cost of equity = 4.25% + (0.7 x 6.75%) = 8.975%
Company B's cost of equity = 4.25% x (1.45 x 6.75%) = 14.0375%
this means that company B's cost of equity is 14.0375% - 8.975% = 5.0625% higher than company A's cost of equity.
Are there any answer options? I know the answer if you have options
Answer:
$39,345,664.93
Explanation:
The computation of the company worth today is as follows:
Present value of revenues after tax is
= $3,700,000 × 1.46 × (1 - 0.25) ÷ (0.07 - 0.018)
= $77,913,461.54
And, Present value of costs after tax is
= $3,700,000 × 0.82 × (1 -0.25) ÷ (0.07-0.011)
= $38,567,796.61
So, the company worth today is
= $77,913,461.54 - $38,567,796.61
= $39,345,664.93
Answer:
Estimated manufacturing overhead rate= $3 per machine hour
Explanation:
Giving the following information:
Machine Hours Per Unit:
Rings= 6 (1,000 units)
Dings= 11 (2,040 units)
All of the machine hours take place in the Fabrication Department, which has an estimated total factory overhead of $85,200.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 85,200/(6,000 + 11*2,040)= $3 per machine hour