A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Define unit vectors along the x-axis and the y-axis as

respectively.
Then the vector from P to Q is

In component form, the vector PQ is (-8,5).
The magnitude of vector PQ is
√[(-8)² + 5²] = √(89) = 9.434
Answer:
The vector PQ is (-8, 5) and its magnitude is √89 (or 9.434).
Answer:
y = -0.83x - 2
Step-by-step explanation:
Slope intercept form is y = mx+b.
M is the slope: In this case the slope (rise/run) is 10/12. However, the slope is decreasing is that would make it negative.
Now we have: y = -0.83x + b
B represents the y-intercept. The y-intercept here is -2. So our final equation is:
y = -0.83x - 2
Answer:
I think it's B. 5/9(F -32) < 140
Step-by-step explanation: