PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
c. 1/6
Step-by-step explanation:
I hope it helps you...
Answer:
380d + 530t > 21,000
Step-by-step explanation:
Each DVD costs $380, we can represent that as:
380d
Each TV costs $530, we can represent that as:
530t
We add these together to find the total profit:
380d + 530t
The manager predicts that whatever the total profit is, will be more than $21,000. So, we represent that as this:
380d + 530t > 21,000
And that is the final answer.
<em>I hope this helps!!</em>
<em>- Kay :)</em>
For this case, what we are going to do is use the following property:
Multiply an equation by a scalar.
In this case, the scalar will be:
k = -2
We have then that equation 2 will be:
k * (4x + y) = k * 1
-2 * (4x + y) = - 2 * 1
-8x-2y = -2
Answer:
The property that justifies this manipulation is:
Multiply an equation by a scalar.
Answer:
Hey there!
We have tangent 29=h/400
Thus, tangent 29 times 400=h
h=221.7 feet.
The height of the kite is 221.7 feet.
Hope this helps :)