1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
STatiana [176]
4 years ago
13

Please help meeee !!!!!! dont ignore this !!!! help whos in need !!!

Mathematics
1 answer:
shutvik [7]4 years ago
8 0
A cardboard box 2 feet, 24 inches, 60.96 cm. box is a perfect square. 
a rectangle

You might be interested in
Nellie has a bankruptcy on her credit report and therefore pays higher interest rates on her current loans. She took out a car l
neonofarm [45]

The amount of extra interest that will be paid is $24300

Since Nellie took out a car loan for $45,000 payable for 6 years at an interest rate of 15%, the interest that she will pay will be:

= ($45000 × 6 × 15) / 100

= $40500

On the other hand, if she hasn't applied for bankruptcy, the amount that she will pay will be:

= ($45000 × 6 × 6) / 100

= $16200

Therefore, the difference between the interest will be:

= $40500 - $16200

= $24300

The correct option is $24300. The given options are incorrect.

Read related link on:

brainly.com/question/25052422

8 0
3 years ago
Read 2 more answers
What the surface area of triangular prism 8cm 10cm 12cm 3cm
horrorfan [7]
The surface area of triangular prism is <span>2880cm
8x10x12x8=2880

hope this helps</span> 
7 0
4 years ago
Read 2 more answers
What is the distance between the points plotted below? If necessary, round your answer to two decimal places.
34kurt
(-1,1) (6,9)
distance = root (x1-x2)²+(y1-y2)²
so root (-1-6)²+(1-9)²= root 113 or 10.6 ≈11
the answer is B. 11.18 units
8 0
3 years ago
Read 2 more answers
An externally imposed project completion time sets the project duration at 75 days. The critical path of the project is establis
Katen [24]

Answer:

3 days

Step-by-step explanation:

This can be seen under Schedule management (Initiating)

Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because

Externally imposed project date = 75 days

Estimated duration of project = 75 days

Hence, a difference in these will be 0

However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration) .

Hence the maximum float in this case will be 0 + 3 = 3 days

8 0
4 years ago
What's 7.2j = $93.24
vfiekz [6]
To find the value of j, divide both sides of the equal sign of 7.2. 

Answer: J= 12.95
8 0
3 years ago
Other questions:
  • A pet-sitting company charges $25 to board a pet for one day. It also charges all customers an extra $7.50 to trim the pet's nai
    12·1 answer
  • A cylindrical roller 2.5 m in length, 1.5 m in radius when rolled on a road was found to cover the area of 16500 m2 . How many r
    10·1 answer
  • Compare. the values and order them from least to greatest. 3.65 feet 4.1 feet 3 11/16 feet
    15·1 answer
  • Write a number pattern for 8 starfish if each had 5 arms?
    15·1 answer
  • What is the formula to calculate the slope?
    15·2 answers
  • Mikayla bought 5 skirts at $x each. Three of the 5 skirts came with a matching top for an additional $9 each. Write and simplify
    14·1 answer
  • For the polynomial below, what is the power of the term with the coefficient of 6?
    9·2 answers
  • Mr. Dunn is moving 25-pound sandbags. His truck can carry ton. He knows that 1 ton equals 2000 pounds. What is the greatest numb
    12·2 answers
  • The population of Friendly City is 150% of what it was 10 years ago. If its population was 25,000 what is its population now?
    6·1 answer
  • How do I simplify? I forgot, it's been a little.
    14·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!