Answer:
It is 27.4
Step-by-step explanation:
First you need to find the area of the three rectangle.
Area=base*high
You do 4*2 for about 3 times
Which is 8 for 4*2
Then you multiply it 3 more time and get 24.
After that you add 24+1.7+1.7 and get 27.4
Answer: H
Step-by-step explanation:
If you assume doubling the workers will halve the time taken to finish then 12 analysts will take 21 days
To finish in 7 days (1/6 of 42 days) you would need 6 x the original number = 36 analysts.
Brook’s Law (see Wikipedia) suggests than adding extra analysts will actually slow the project down!
One reason is the extra people tend to get in each others way.
Answer:
D not here
Step-by-step explanation:
A-2 is not reasonable as it is not possible
C- bot possible
B- maybe
D- most reasonable