Answer:
Materials quantity variance = $1,750(U)
Explanation:
Standard quantity(SQ) = $2.5 * 6600 = 16500 Kg
Standard Price( SP) = $5
Actual quantity(AQ) = 16,850 Kg
Actual Price( AP) = $90,720 / 18,900 kg = $4.8
Materials quantity variance = SP * (SQ - AQ)
Materials quantity variance = 5 * ( 16500 - 16,850 )
Materials quantity variance = 5 * (350)
Materials quantity variance = $1,750(U)
In risk management, risk evaluation involve Risk resolution. The evaluation process is carried out by management.
<h3 /><h3>What is Risk?</h3>
Risk is the threat of things going wrong or having a negative impact on the operations of the organization. The risk can be of many types including and not limited to audit risk, control risk, credit risk, business risk, inherent risk, financial risk and more.
Risk is evaluated by the management to minimize the effects and mitigate the risk. There are several steps that are performed to analyze the risk and many ways are there to lower the effects of risk.
Risk resolution is the management strategies to analyze the risk and the best ways to mitigate the effects. Transfer the risk, avoid the risk by changing the decision, reduce and accept.
Learn more about Risk at brainly.com/question/27247805
#SPJ1
Accord According to the California Insurance Code, any individual who unwilfully takes part in an out of line strategy for rivalry is obligated to the state for a fine of up to $5,000 per infringement. In the event that the demonstration is resolved to be headstrong, the fine won't surpass $10,000 per act.
I feel that D would be the correct answer because of new technology
Answer:
30,000 units
Explanation:
Budgeted sales is 30,000 units
Beginning inventory = 5000 units
Ending inventory = 5000 units
In order to meet the sales of 30,000 units, the sum of budgeted production and beginning inventory must be at least 30,000 units. However, since the company desires to have 5000 units in ending inventory, this sum must be raised to 35,000 units, which means the production needs to 30,000 units
--> Budgeted production = 30,000 + 5000 - 5000
= 30,000 units