is the total implied increase in economic spending activity from a government stimulus of
billion
<u>Explanation:
</u>
The median product preference tests the increase in expenditure due to changes in availability.
In increasing government expenditure, total economic investment would be increased by the scale of the budget multiplier. In other terms, the expenditure equation indicates how much GDP can increase as government expenditure increases.
The spending multiplier can be expressed as 

So, the total implied increase in economic spending is 
In economics, marginal propensity to consume (MPC) is the proportion of an aggregate raise in pay that consumer spends on the consumption of services and goods, as opposed to saving it.
Answer and Explanation:
The computations are shown below:
1. For annual implicit cost
= Earning annual salary + earned annual interest
= $80,000 + $500
= $80,500
2. For Annual accounting cost
= Explicit cost
= Direct expenses
= Office rent + rent of equipment + supplies + utilities + salary of a book keeper
= $15,000 + $3,000 + $1,000 + $1,200 + $35,000
= $55,200
3. For economic cost
= Accounting cost + implicit cost
= $55,200 + $80,500
= $135,700
4. For revenue
= Accounting profit + profit
= $55,200 + $50,000
= $105,200
5. For revenue
= Economic cost + profit
= $135,700 + $50,000
= $185,700
Answer:
Correct option is (C)
Explanation:
Given:
Face value of bond (FV) = $1,000
Coupon rate = 6.2% annual and 6.2 / 2 = 3.1% semi annual
Coupon payment (pmt) = 0.031 × 1,000 = $31
Maturity period (nper) = 8×2 = 16 periods
Rate = 8.3% annual or 8.3 / 2 = 4.15%
Present value of bond can be computed using spreadsheet function =PV(rate,nper,pmt,FV)
Present value of bond when yield is 8.3% is $878.99
If ytm increases to 8.6% annual or 8.6 / 2 = 4.3% semi annual, then present value of bond will be $863.22 (using spreadsheet function again)
It can be seen that as ytm increased from 8.3% to 8.6%, price of bond fell by $15.77 approximately (878.99 - 863.22)
The amount that Carlos can deduct for rent in the year 2021, based on his annual rent is <u>c.$1,000.</u>
<h3>Rent in 2021</h3>
When recording rent, you can only record it for the period that the financial statement is for.
The rent given is for 18 months from December 2021 which means that it will be for only a single month in December.
The rent will therefore be a rental amount for a month:
= Rental amount / Number of months
= $18,000 / 18
= $1,000
In conclusion, option C is correct.
Find out more on prepaid rent at brainly.com/question/1079277.
Construction contracts often include a provision awarding damages to the buyer at "X" amount of dollars per day for each day the builder is late in completing the work. The parties to the contract agree on this amount in advance because they know the buyer will incur added costs, or will lose profits, because of the delay. If the amount fixed for the damages is unreasonably high, the court will consider it a <u>Penalty</u> and will not enforce it.
Explanation:
<u>"Construction Contract" can be defined as a combination of various individual documents which focuses on the different aspect of the project, or it can also be a multi-page document which contains various sections that offers details on different aspects of the agreement.</u>
<u />
A construction contract includes
- Name of contractor and contact information.
- Name of homeowner and contact information.
- It describes property in legal terms.
- The various list of attachments of the contract.
- The cost involved
- Description of the work and its completion date.
- Right to stop the project.