True.
At 200 feet you turn on low beams :)
Answer:
Simple payback is 4 years
Total discounted Payback is more than the 5 years which is the payback cutoff period.
Explanation:
Payback period is the time period in which the project recovers the initial cost incurred. Lower the payback period the more beneficial will be the project.
Simple payback = $100,000 / $25,000 = 4 years
Discounted Payback
Discounted payback is calculated by using the present value of future cash flows.
Total discounted cash flows = 22935.78 + 21042.0 + 19304.59 + 17710.63 + 16248.28 = 97,241.28
As sum of all cash flows are less than the initial investment so, total discounted Payback is more than the 5 years which is the payback cutoff period.
Answer:
A. UPC
Explanation:
A UPC is an acronym for universal product code. UPC is typically used for the identification of a specific product and its manufacturer (vendor) through a unique code that is printed on the product.
Basically, a universal product code (UPC) comprises of two (2) main parts;
- A machine-readable barcode that contains sets of vertical black lines.
- A unique twelve (12) digit number placed beneath or adjacent to the machine-readable barcode.
The first six-digits of the UPC represents the manufacturer and is printed on all of its products while the next five-digits is the product's unique reference number (item number) and the last digit is typically known as a check digit, used for the verification of the authenticity of a UPC.
Generally, the universal product code are usually scanned with a barcode scanner and this makes it easier to identify a product, as well as its price.
<em>Hence, a universal product code (UPC) contains data that identifies a product. </em>
Answer:
The correct answer is B: the jobs produced during the period have been under-costed
Explanation:
Giving the following information:
If manufacturing overhead has been under-allocated during the period, then which of the following is true?
(a) the jobs produced during the period have been over-costed
(b) the jobs produced during the period have been under-costed
(c) the jobs produced during the period have been costed correctly
(d) none of the above
When manufacturing overhead has been under-allocated means that the actual costs incurred where superior that the estimated cost for the period.