1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
ss7ja [257]
3 years ago
7

In the project briefing, the outgoing project manager tells you that the scope statement for the project has been documented, WB

S has been created by subdividing the major project deliverables into smaller, more manageable components and an activity list has been prepared. What should you do NEXT?
Business
1 answer:
zloy xaker [14]3 years ago
3 0

Answer:

I should  verify scope that involves formalizing acceptance of the project deliverables.

Explanation:

5- In this stage of project scope management, key project stakeholders (customer and sponsor for the project) inspect in order to formally accept the deliverables during this process. If  happen that deliverables are not acceptable, then the customer/sponsor can requests changes. So, as a consequence, the main outputs of this process are:

- accepted deliverables

-  change requests

- work performance information

- updates to project documents.

6- Controlling scope: This is about controlling changes to project scope throughout the life of the project. Scope changes regularly influence the team's ability to meet project time and cost goals, that's why the project managers must carefully weigh costs and benefits of scope changes.The main results of this process are:

- Work performance information

- Change requests

- Updates to the project -management plan

- Project documents

- Organizational process assets.

You might be interested in
The reported net incomes for the first 2 years of Sarasota Products, Inc., were as follows: 2020, $155,500; 2021, $188,100. Earl
Phoenix [80]

Answer:

Dr retained earnings($21,600+$15,800) $37,400.00

Cr  accumulated depreciation                                         $21,600

Cr inventory                                                                       $15,800

Explanation:

The errors that require adjustment are the overstatement and understatement of depreciation expense as well as the December 2021 overstatement of inventory.

The understatement of inventory in 2020 would have self-corrected itself in 2021 since closing inventory in 2020 deducted from costs of goods available  for sale would be introduced as opening inventory in 2021.

net effect of depreciation=understatement -overstatement=$37,500-$15,900=$21,600.00

hence retained earnings would reduce by $21,600.00

for the overstatement of inventory,retained earnings would reduce by $15,800

5 0
2 years ago
Upon graduating from college this year, you expect to earn $25,000 per year. If you get your MBA, in one year you can expect to
Novosadov [1.4K]

Answer:

Income difference= $8,250

Explanation:

Giving the following information:

Actual salary= $25,000 per year

MBA salary= $35,000 per year.

Inflation rate= 5 percent.

We will separate the analysis. First, we will calculate the nominal increase. Then, the real increase based on purchasing power.

In nominal terms, the increase in income is equal to the difference between salaries.

Income increase= 35,000 - 25,000= $10,000 increase.

In real terms, we need to calculate the effect of inflation on your purchasing power.

Actual income= $25,000

MBA income= 35,000*0.95= $33,250

Income difference= $8,250

In other terms, the real purchasing power of the MBA income decreases. Therefore, the difference today between real salaries is lower than the nominal difference.

6 0
3 years ago
Generally, a high ___________ ratio could lead investors and creditors to view the company as being very risky debt to owners' e
Ipatiy [6.2K]

High <u>debt to owner's equity ratio. </u>

This is total liabilities divided by total assets and shows a company's financial leverage, also known as their ability to handle current and future financial obligations.

6 0
2 years ago
Read 2 more answers
The Work Breakdown Structure (WBS) is normally developed by listing deliverables - major deliverables first and then progressive
AURORKA [14]

Answer:

The correct answer is True.

Explanation:

The steps to follow to create a work breakdown structure are as follows:

1. Organize a meeting and share with the main stakeholders: team members are one of the most valuable assets in the process of creating the work breakdown structure. They have the knowledge, experience and creativity necessary to define each deliverable reaching the most specific details.

2. Complete the definition of all project deliverables: it is about going one step beyond the level reached in the planning and 100% complete the information on all project deliverables, including internal and external, associating each one with its estimated completion time.

3. Break down each deliverable into smaller, more manageable parts: it is about achieving a realistic level of work planning by the project manager, which ensures that, without interfering with the total estimated project deadline and the overall plan, it can be completed by the work teams. It is about determining work packages. These units constitute the lowest level of the EDT and are pieces of work that are specifically assigned to a person or a team of people to be completed, under the supervision of the Project Director. It is recommended that they focus on a single point of responsibility. The work packages will be used later to define the activities and tasks in which the project is divided.

4. Review the results obtained: with the stakeholders, both at the time of finalizing the elaboration of the work breakdown structure, and when modifications or updates are included, if applicable. It is essential to avoid overlaps.

7 0
3 years ago
During March, the production department of a process operations system completed and transferred to finished goods 25,000 units
never [62]

Answer:

$2.10

Explanation:

The computation of the cost per equivalent unit for direct material is shown below:

= (Direct material cost + Beginning inventory cost) ÷ (equivalent units for the materials)

where,

Equivalent units would be

= Completed and transferred units + beginning work in progress units + additional units

= 25,000 + 110,000 + 30,000

= 165,000 units

And, all the other things would remain the same

= ($253,000 + $93,500) ÷ (165,000 units)

= $2.10

Since all the units are completed with 100% and we consider it same

7 0
3 years ago
Other questions:
  • One of the primary causes of non-conforming supplier quality involves inconsistent communication and the resultant mis-understan
    13·1 answer
  • The concept of "benchmarking" is: a. The process of comparing a particular company with a subset of the competitors in the indus
    5·1 answer
  • What is the fourth part to property rights?
    10·1 answer
  • The law of comparative advantage explains why a. specialization and exchange will make it possible for trading partners to expan
    9·1 answer
  • Information is power. Withholding or distorting project information is aviable and potentially useful approach to increase power
    8·1 answer
  • You have $11,000 and will invest the money at an interest rate of .33 percent per month until the account is worth $17,200. How
    5·1 answer
  • WILL GIVE BRAINIEST 3 SENTENCES OR MORE
    9·1 answer
  • Each of these is a key topic to consider when researching a potential employer. company products or services, company customers,
    6·1 answer
  • What are measurements that evaluate results to determine whether a project is meeting its goals?.
    9·1 answer
  • The first mall in mumbai, india​ was successful. Builders proceeded to construct three more right away. However, they have more
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!