Answer:
B. between -2 and -1
Step-by-step explanation:
Brainlyist please
Answer:
Temperature is measured in units of temperature.
In SI units, it is K (degrees Kelvin).
In CGS units, it is °C (degrees Celsius)
In English units, it is °F (degrees Fahrenheit)
Therefore the mean and standard deviation will be measured in the selected units for temperature.
Answer:
166.5 m³
Step-by-step explanation:
Vcone = ⅓ × pi × r² × h
pi × r² × h = 3 × Vcone
Vcylinder = pi × r² × h
Vcylinder = 3 × Vcone
Vcylinder = 3 × 55.5 = 166.5 m³
Answer:
case 2 with two workers is the optimal decision.
Step-by-step explanation:
Case 1—One worker:A= 3/hour Poisson, ¡x =5/hour exponential The average number of machines in the system isL = - 3. = 4 = lJr machines' ix-A 5 - 3 2 2Downtime cost is $25 X 1.5 = $37.50 per hour; repair cost is $4.00 per hour; and total cost per hour for 1worker is $37.50 + $4.00
= $41.50.Downtime (1.5 X $25) = $37.50 Labor (1 worker X $4) = 4.00
$41.50
Case 2—Two workers: K = 3, pl= 7L= r= = 0.75 machine1 p. -A 7 - 3Downtime (0.75 X $25) = S J 8.75Labor (2 workers X S4.00) = 8.00S26.75Case III—Three workers:A= 3, p= 8L= ——r = 5- ^= § = 0.60 machinepi -A 8 - 3 5Downtime (0.60 X $25) = $15.00 Labor (3 workers X $4) = 12.00 $27.00
Comparing the costs for one, two, three workers, we see that case 2 with two workers is the optimal decision.