Answer:
areas of high pressure to areas of low pressure
I believe it would be 3 because the higher the number the less acidic and the more basic it is.
The estimated expected (mean) time for project completion is 50 weeks, time management includes all the activities necessary to achieve the target date of delivery of the project. It includes the following activities: identification of activities, logical sequencing of activities, estimation of duration of activities, and preparation of the project schedule. For the preparation of the schedule we will see various methods such as resource leveling, simulation, and the critical chain method.
Answer:
Key points
Neurons communicate with one another at junctions called synapses. At a synapse, one neuron sends a message to a target neuron—another cell.
Most synapses are chemical; these synapses communicate using chemical messengers. Other synapses are electrical; in these synapses, ions flow directly between cells.
At a chemical synapse, an action potential triggers the presynaptic neuron to release neurotransmitters. These molecules bind to receptors on the postsynaptic cell and make it more or less likely to fire an action potential.
Explanation: