Answer:
Delayed, accelerated
Explanation:
Total or aggregate slack, is the term which is defined for the activity, is the time that this activity could delayed without impacting on the final date of the project.
It can be computed as the:
Smaller value of Late finish - Early finish field
and
Late start - Early start field
So, when project has positive total slack, few activities delayed the completion of project and when the project has negative total slack, then few activities accelerated to finish the project.
Answer:
The right approach is Option C (global minimum variance portfolio).
Explanation:
- A completely-invested portfolio with either a low uncertainty factor seems to be the GMV portfolio. This same GMV portfolio corresponds to or is situated mostly on the left end including its FI-efficient frontier.
- Although aside from either the full-investment requirement, no restrictions are enforced, the GMV portfolio deals for analytical portrayal.
The latter options offered are not relevant to something like the scenario presented. So that is indeed the correct solution.
Answer: 6.91%
Explanation:
Expected return = Sum of (Probability of state of economy * Return given state of economy)
= (56% * 8%) + (12% * 25%) + (19% * -3%)
= 4.48% + 3% - 0.57%
= 6.91%
Answer:
The combined wage bracket tables in Exhibits 9-3 and 9-4 is missing hence I will use 2014 tax year
answer :
a) Federal income tax withheld
= 75.6 + ( 1989.60 - 944 )*15% = $232.44
b) social security
6% * 1989.6 = $119.38
c) Medicare
1.45% * 1989.6 = $28.85
Explanation:
For a single individual
Two withholding allowance = $329.20 * 2 = $658.40
Gross Pay = $2648
withholding allowance = $658.40
Subject to withholding = $2648 - $658.40 = $1989.60
a) Federal income tax withheld
= 75.6 + ( 1989.60 - 944 )*15% = $232.44
b) social security
6% * 1989.6 = $119.38
c) Medicare
1.45% * 1989.6 = $28.85