Answer:
$112,500
Explanation:
July August September October
Credit Sales(90000*75%) 67,500
(110,000*75%) 82,500
(120,000*75%) 90,000
Cash Sales (120,000*25% 30,000
<em>Total Cash expected to be collected in September will be;</em>
Credit Sales of August $82,500
Cash Sales of September $30,000
Total cash expected to be collected in September =$112,500
Answer:
compliance risk
Explanation:
Compliance risk -
It refers to the risky situation , which can be due to some financial forfeiture , legal penalties , loss of material , when the company fails to follow the rules and regulations , is referred to as compliance risk .
Hence , from the given scenario of the question,
The correct type of risk involved is compliance risk .
Answer:
Explanation:
1. To find the cost per unit of production, first we find the total cost. So we multiply the unit of each factor used times its cost.
capital: 2*$10=$20
raw materials: 5*$4=$20
labour: 8*$3=$24
Total cost: $20+$20+$24=$64
Then we divide the total cost over the total units produced:
Cost per unit: $64/640=$0,1 Answer is B
2. If the cost per unit of raw materials increases from $4 to 8$. Then the total cost of production will be:
capital: 2*$10=$20
raw materials: 5*$8=$40
labour: 8*$3=$24
Total cost: $20+$40+$24=$84
To find how much the cost per unit will rise, to find how much it rises
64$→100%
$84←x
x=($84*100%)/$64=131.2%
131.2%-100=31.2%. The answer is B
3. Because there is a change in raw materials, then there would be changes in the supply demand. In this case, the total cost and the cost per unit increased, then it is a negative shock to the supply demand. This is represented as a shift to the left. The answer is D
Answer:
Year Dry Prepreg discounted cash flow
0 -$30,000 -$30,000
1 10,000 8,772
2 10,000 7,695
3 10,000 6,750
4 10,000 5,921
5 10,000 5,194
Year Solvent Prepreg. discounted cash flow
0 -$90,000 -$90,000
1 28,000 24,561
2 28,000 21,545
3 28,000 18,899
4 28,000 16,578
5 28,000 14,542
a. Calculate NPV, IRR, MIRR, payback, and discounted payback for each project
Dry Prepreg
NPV = $4,330
IRR = 19.86%
MIRR = 17.12%
payback = 3 years
discounted payback = 4.17 years
Solvent Prepreg
NPV = $6,130
IRR = 16.80%
MIRR = 15.51%
payback = 3.21 years
discounted payback = 4.58 years
b. Assuming the projects are independent, which one(s) would you recommend?
- both projects, since their NPV is positive
c. If the projects are mutually exclusive, which would you recommend?
Dry prepreg becuase its IRR, MIRR are higher, and its payback and discounted payback periods are shorter.