Answer:
The answer is c because you would plug in -2 for x and -6 for y
Step-by-step explanation:
I believe the answer is either 5 or -1.5
4n - 7 = 13
7 - 4n = 13
4(5) - 7 = 13
7 - 4(-1.5) = 13
4(5) - 7 = 13
If George completed 3/5 of work in 9 days, it means that he needs 3 days to finish 1/5th of the work.
The remaining part is 2/5 because 1-3/5=2/5. 2/5 is also 6/15
From this, how much did George do? in the first 3 days he did 1/5th and then one more day was left, during which he did 1/5/3=1/15th.
So he did in total 1/15+1/5=1/15+3/15=4/15.
this means that Paul did the rest of 6/15, so Paul did 6/15-4/15=2/15.
So we know that he does 2/15 in 4 days, which means that every two days he can do 1/15 of the work
so he would need 15 times 2 days to finish the work - 30 days!
Answer:
-3.5x + 3y - 3
Step-by-step explanation:
1.2x + 3y - 3 - 4.7x
=> -3.5x + 3y - 3
Therefore, our simplified expression is -3.5x + 3y - 3
Hoped this helped.