Answer: Self-interest, competition, and incentives promote smoothly running markets. Unforeseen events disturb supplies of goods and services and affect prices in the marketplace. Rising prices, specialization, negative incentives, and multiple markets.
Explanation: Hope this helps :)
Answer:
Answer for the question:
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:
Immediate
Activity
Designation
Predecessor
Time in Days
Break down both machines
A
None
3
Clean machine 1
B
A
3
Clean machine 2
C
A
3
Re-set machine 1
D
B
1
Re-set machine 2
E
C
2
Re-calibrate both machines
F
D and E
1
Final test
G
F
2
Using the Single Time Estimate CPM procedure, what is the critical path for the project & the overall project duration?
e. ABCDG & 10 days
c. ABDFG & 10 days
d. ABDFG & 11 days
b. ACEFG & 10 days
a. ACEFG & 11 days
is given in the attachment.
Explanation:
The term that best fits the blank provided above is LOYALTY CARD. This kind of system allows the provision of rewards and incentives for consumers and this would also allow detailed recording and the tracking of the activities of the consumers. Hope this helps.
This is known as Data Visualization