Answer:
Both the metric system and the US monetary system are based on the system of tens.
Explanation:
The metric system is based on the meter, which is divided into 100 centimeters, while the US monetary system is based on the dollar that is divided into 100 cents.
Generally speaking all Americans and most US organizations use the Imperial System (along with Liberia and Myanmar), while the rest of the world uses the metric system. But some American organizations use the metric system also, like the military and many financial institutions, specially those that export or trade with commodities.
What s really intriguing about this, is that the metric system is the official measuring system of the US since 1866, but it hasn't been massively applied yet.
Answer:
B) The letter of intent is an invitation to negotiate, which is not an offer.
Explanation:
A letter of intent is simply an invitation to negotiate any type of transaction, sales or lease. The amounts included in the letter can serve as a basis for the negotiating or bargaining process, but they are not fixed and even Ryan can change them. This is similar to an ad in a newspaper that offers something for sale. Until the bargaining process is over and both parties agree on the consideration exchange and other terms, it is just a notice without any legal value.
In the efficiency wage model with the efficiency wage above the market-clearing wage, the level of employment depends on: labor demand alone.
<h3>What is wages model?</h3>
Wages model is a model that stated that wages which a worker or an employee earn is based on the workforce or the amount of money available to pay the workers.
In a situation were will have wage that is above the market-clearing wage this tend to mean that the level of employment will depends on labor demand only.
Therefore the level of employment depends on: labor demand alone.
Learn more about wages model here:brainly.com/question/1622389
#SPJ12
Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.