Pretty simple. Ever heard of the saying 'More minds are better than one'? Well, it's true. Not only would you come up with better answers with a shared opinion, your opinions and ideas are less biased from past experiences, so they are more accurate every time!. Plus, in terms of a team collab, tasks can be completed faster if everybody focuses on different things instead of one.
:)
 
        
                    
             
        
        
        
The Internet Simulator is a tool developed by Code.org for our new high school Computer Science Principles class. ... The Internet Simulator was designed to be used in a classroom with students working collaboratively in-person to solve problems.
        
             
        
        
        
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish. 
The essential technique for using CPM is to construct a model of the project that includes the following:
-     A list of all activities required to complete the project (typically categorized within a work breakdown structure),
 
-     The time (duration) that each activity will take to complete,
 
-     The dependencies between the activities and,
 
-     Logical end points such as milestones or deliverable items.       
 
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.