Answer:
It will take the apprentice 24 days working alone
Step-by-step explanation:
Let the number of days it takes the apprentice be x
It will take the landscaper x/3 ( since he is three times faster)
The rate for both will be 60/6 = 10 sq m per day
Rate for apprentice is 60/x
rate for the boss is 60/x/3 = 180/x
Adding the rates together;
60/x + 180/x = 10
240/x = 10
240 = 10x
x = 240/10
x = 24 days
The answer is choice C) All real numbers from 0 through 35.
The domain is the set of allowed inputs (x). The points on this graph have x coordinates that span from x = 0 to x = 35. Because x is time in minutes, we can have fractions of a minute (eg: x = 7.5 ---> 7 and a half minutes). So we won't just have integers.
The answer for this question is Y=3x+1