1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
8090 [49]
3 years ago
9

Which of the following is a major benefit of a peer to peer network?

Computers and Technology
2 answers:
boyakko [2]3 years ago
6 0

Answer:

that people can help each other

Explanation:

Oksi-84 [34.3K]3 years ago
6 0

No need to store files on an external server, much more secure method of file transport from person to person

You might be interested in
A method signature for a method consists of all elements of the method except the body. That is, a method signature consists of
Bess [88]
To be honest I feel like it’s B that’s looks and seems the most correct to me
8 0
3 years ago
When you are almost done with your soup and want to get at the last little bit, how should you do this 2
pav-90 [236]

Answer:

<u>B. Tip the bowl slightly, then spoon up the last bit</u>

Explanation:

Generally speaking none of the other answers made much of sense.. "tip the bowl from side to side" doesn't help you at all, neither does "Keep spooning as much as you can, then stop eating". Neither of these will help you spoon up the last little bit, <u>the most logical answer is B. "Tip the bowl slightly, then spoon up the last bit"</u>. If this is not the correct answer then it'd be D, but I don't believe/feel that it's "poor etiquette" to "leave the last little bit".

7 0
3 years ago
Differentiate between refraction of light and reflection of light
lapo4ka [179]

Refraction represents a change in the direction of propagation when beams of light encounter a medium with a different density.

Reflection is the return of light to the medium it came from when it encounters a mirror.

3 0
3 years ago
Read 2 more answers
An elevator of mass 250kg is carrying two persons whose masses are 50kg and 100kg. if the force exerted by the motor is 3000N. C
Agata [3.3K]

m_{elevator}=250kg \\m_{people}=50kg+100kg=150kg \\m_{motor}\approx3000N\div10\frac{m}{s^2}\approx300kg \\m_{total}\approx250kg+150kg+300kg\approx\boxed{700kg}

Hope this helps.

r3t40

5 0
3 years ago
With respect to PERT and​ CPM, slack A. is a task or subproject that must be completed. B. marks the start or completion of a ta
Wewaii [24]

Answer:

The correct answer is C) With respect to PERT and​ CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.

Explanation:

The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.

Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.

There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.

The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.

That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.

8 0
3 years ago
Other questions:
  • Susan bought a new sweater on sale for $28.93.she was charged HST of 13%.find the total amount of her bill including taxes.​
    9·1 answer
  • The two key elements of any computer system are the____and the _____.
    7·1 answer
  • Escribe, en los siguientes cuadros, los conceptos que correspondan
    10·1 answer
  • Write a program to read data from a file named problem 2. ext. This file has three exams data (floating point data) in three col
    11·1 answer
  • Hi, I just have a few questions from my digital tech assignment.
    14·2 answers
  • Consider the program below: public class Test { public static void main( String[] args ) { int[] a; a = new int[ 10 ]; for ( int
    5·1 answer
  • What is software piracy?
    11·1 answer
  • In _____, a program running on a Web server creates a Web page in response to a request for specific information from a Web clie
    7·1 answer
  • List and explain three computing devices from the 20th century​
    13·2 answers
  • What component of a change management program includes final testing that the software functions properly
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!