Answer:
21 weeks
Step-by-step explanation:
In this question, we are to use proportionality to find the solution to the question.
We were made to know that the time taken to build the highway is varied directly with the length and inversely with the number of workers.
Let us make a mathematical representation for this.
Let the time be t, number of workers be w and length be l
t is directly proportional to l and inversely proportional to w
Mathematically;
t = kl/w
Where k is the constant of proportionality.
Let’s find the value of k
150 workers built 12 miles of highway in 14 weeks ; plug these in the equation to get k
14 = k * 12/150
k = 150 * 14/12 = 175
Now we want to get t given w and l
from ;
t = kl/w
We can get t; where l = 15 and w = 125
t = 175 * 15/125
t = 21 weeks
7*2=14
14*3=42
Michelle is 42 years of age...
Convert 3/4 to a denominator of 8 by multiplying by two, getting you:
6/8 + 1/8
Add those and you get D) 7/8
Answer:
x = (2+√10)/ 3 and x= (2-√10/3)
Step-by-step explanation:
g(x) = -3x² +4x +2
use the quadratic formula x= (-b±√b²-4ac)/2a, when g(x) = ax² +bx +c
x= [-4 ±√4²-4*(-3)*2] / 2*(-3) , solve under the square root
x= (-4 ± √16 +24) / -6 , add under the radical
x= (-4 ±√40) / -6, simplify the square root
x= (-4 ±2√10) /-6, factor -2
x= -2 (2±√10)/-2 *3, simplify -2
x= (2±√10)/3
Therefore,
x = (2+√10)/ 3 and x= (2-√10/3)
You would just do 3/5 * 55 = 33 movies were new releases.