Answer:
it will help get into college.
Explanation:
a diploma doesn't open the doors to all jobs. also, if you want a higher pay for most jobs, you won't be able to get it with a diploma.
a diploma can open the doors to a college, though. which will help you further your education, and get a degree that can open the doors you need
Answer:
The amount of effective interest expense that chaco will record in the first six months is $14,375
Explanation:
interest payment that will be first made is on June 30, Year 1. Therefore, the outstanding balance used in the calculation is the issue price.
The interest expense is calculated by these formula
Interest expense = Effective semiannual interest rate × Outstanding balance
Interest expense = (8% ÷ 2) × $359,378 = $14,375
So the interest expense is gotten as %14,375
Answer: C. both Tim and Bev to be marginally attached workers
Explanation: The Bureau of Labor Statistics considers both Tim and Bev as marginally attached workers.
Usually, marginally attached workers refers to individuals who are not actively seeking for a job or employment at a particular point in time,which is the case of both Tim and Bev. However, for an individual to be classed as a marginally attached worker, He or she must be willing and able to work and worked or sought for a job at any point within the last twelve months. Bev has searched for a job within the last year and Tim's environment has very few openings to accommodate employees.
Answer:
PV= $2,749,494
Explanation:
Giving the following information:
Cash flow= $200,000
Number of periods= 25
Interest rate= 5.25%
<u>First, we need to calculate the future value using the following formula:</u>
FV= {A*[(1+i)^n-1]}/i
A= annual cash flow
FV= {200,000* [(1.0525^25) - 1]} / 0.0525
FV= $9,881,102.14
<u>Now, the present value:</u>
PV= FV/(1+i)^n
PV= 9,881,102.14 / (1.0525^25)
PV= $2,749,494
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.