Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Morgan will get $1600 with the process of simple interest.
<h3>what is simple interest?</h3>
Simple interest is calculated based on a loan's principal or the initial deposit into a savings account. Simple interest doesn't compound, therefore a creditor will only charge interest on the principal sum, and a borrower will never be required to pay further interest on the interest that has already accrued.
Rate of interest = 12%
principal = $1000
Time = 5 years
Simple interest

Now amount = 1000+600 = 1600.
Therefore, Morgan will get $1600.
To learn more about simple interest from the given link
brainly.com/question/25793394
#SPJ4
Answer:
correct option is B: $29,000
Explanation:
given data
apartments = 15
family homes = 45
office buildings = 25
pay for cleaning staff = $12.50/hour
solution
we get here Total Budgeted hours that is
type Number Hrs/Clean No of Cleans Total Hours
Apartments 15 4 4 240
Homes 45 6 4 1080
Office 25 10 4 1000
Total Budgeted hours need per month 2320
Budgeted cost per month that is 12.50/hrs so it will 29000
so correct option is B: $29,000
Answer:
En la actualidad existen diversos enfoques teóricos de la administración, entre los cuales se encuentran:la teoría científica de la administración la teoría clásica de la administración la teoría de Las relations humanas la teoría científica del comportamiento , la teoría de Los sistema, la teoría burocrática
420 is what I got. if you do two divided by 120 it gives you 60 then 60 times 7 is 420.