Answer:
The correct answer is option a.
Explanation:
Apples and oranges are substitutes. An increase in the price of oranges will cause the demand for apples to increase. This is because people will prefer a cheaper substitute. This increase in the demand for apples will cause its demand curve to shift to the right.
The rightward shift in the demand curve will cause the equilibrium price to increase. But this change in price will not cause a change in demand. The change in price affects only the quantity demanded. Change in demand happens because of a change in other factors.
So, the given statement is not correct.
It should be noted that money invested is to C. Achieve long-term goals
<h3>What is money?</h3>
It should be noted that money is a means of exchange. It is required for our transactions.
When money is invested, the purpose is simply to achieve long-term goals. This can be an increase in revenue, prepare for future financial needs, etc.
Learn more about money on:
brainly.com/question/24373500
Answer:
Journal Entry
Explanation:
Cash Dr, $63,360
Loss on sale receivable Dr, $6,640
Receivable from factor Dr, $6,200
To resource liability $4,200
To Accounts receivable $72,000
(Being transfer on the books of Mountain High is recorded)
Working Note :-
2% × $72,000 = $1,440
Cash = ($72,000 × 0.90) - ($72,000 × 0.02)
= $64,800 - $1,440
= $63,360
Loss on sale receivable = ($4,200 + $72,000) - ($63,360 + $6,200)
= $76,200 - $69,560
= $6,640
Answer:
Hi there!
C. Debit Miscellaneous Expense $270; credit Cash $270.
Explanation:
At the time of the reimbursement from the petty cash, the vouchers for the money used are presented and these must be charged to the different expenses incurred.
In October 1, the journal entry for the petty cash increase of $54 will be:
Debit Petty Cash $54; credit cash $54.
The work breakdown structure must be the basis for a project cost estimate if you plan to create a cost baseline and use earned value management as part of monitoring and controlling costs.
Work can be made more manageable and approachable by using a common productivity strategy called task breaking. The Work Breakdown Structure (WBS), one of the most significant projects management papers, is the tool that applies this technique to projects. It does it on its own, integrating scope, cost, and schedule baselines to guarantee project plans are in sync.
The Work Breakdown Structure is a "deliverable-oriented hierarchical decomposition of the work to be completed by the project team," according to the PMI Project Management Book of Knowledge (PMBOK). WBS can be divided into two categories: deliverable-based and phase-based. The deliverable-based strategy is the most popular and preferred method. The Elements listed in the first Level of the WBS are the primary distinction between the two methodologies.
Learn more about project costs here brainly.com/question/15518327
#SPJ4