Answer:
0.038 units per $ of factor costs
Explanation:
Labor cost for 40 units = 30 hours × $10/hour = $300
Cost of paper for 40 units = 15 sheets × $50/sheet = $750
Output = 40 units
Multi factor productivity is expressed as;
Multi factor productivity = Output/Total Factor cost
Multi factor productivity = 40 units/$1050 = 0.038 units per $ of factor cost
Multi factor productivity is a measure that depicts units produced for every $ of factor products used. In the above case 2 factors i.e labor and paper are used.
The answer is "polyphonic"
Hope this helps:)
Answer: contingency
Explanation:
Contingency planning is a form of planning that is used by an organization in order to plan ahead in case an event occurs. Contingency plans can also be called a 'Plan B' due to the fact that it's an alternative action in case things does not go as planned.
Therefore, based on the question, Pinnacle is practicing contingency planning.
1) C
2)B
3) A Hoped this helped you!