Answer:
C. Debt to Income Ratio
Explanation:
The debt to income ratio (DTI)provides a picture of the level of debts of a borrower. The DTI is usually expressed as a percentage of gross income. A high debt to income ratio indicates a person spends a high percentage of income on paying debts.
Lenders use the debt to income ratio to assess a borrower's ability to repay debts. Individuals with low DTI are preferred to those with a high one.
Answer:
E) existing factory has enough capacity to handle demand for the new products as well as the existing products.
Explanation:
If the existing factory doesn't have enough capacity to produce both the new product and existing ones, then if doesn't matter if the technology used is the same, or the new product is an extension of an existing product line, or existing human resources possess the abilities and knowledge required, or even if the product design is already complete or not.
If the factory's production capacity cannot handle the new product, then the company needs to expand the existing factory's production capacity or build a new facility.
Answer:
I believe it is A
Explanation: Recommended Best Practices for Disposable Aerosol Cans. 44 ... Reactivity - A waste is reactive if it reacts violently with water, forms potentially ... K-Listed Wastes: These are hazardous wastes from specific processes, many of ... Appendix C. ... Aqueous clean- ers are less toxic than petroleum- based solvents.
Okay so rewards and penalties make people make better decisions. So like if I don't get questions wrong on a test I receive $5 from my parents, but if I fail a test I'm grounded for a week. So I study more to get money. (this is not actually me just making an example). Rewards make people want to do better, and so do penalties. I don't want to do bad and get punished for it.
Answer:
Explanation:
Reorder point quantity is the level at which an inventory is expected to be restocked , calculated by finding the sum of demand over the lead time and the safety stock days
Daily usage = 800 feet / day
Lead time = 6 days
Desired service level = 95%
Risk level = 1-0.95 =0.05
safety stock at 0.05 = 1800
Reorder point = expected demand in (LT) + safety stock
= (800*6) + 1800
= 4800+1800 = 6600 feet.