Answer:
The correct answer is letter "A": can be used to estimate the projected cost of completing the project.
Explanation:
The Cost Performance Index or CPI measures the projected cost of work completed compared to the current cost spent. The CPI represents a ratio of earned value to actual cost. If the CPI is greater than one, the project is under budget. When the CPI equals one the planned and actual costs are equal. If the CPI is higher than one, the project is over budget.
The Chester company is likely implementing a strategy called
the niche differentiation. This is the process in which helps a specific
organization or company to coexist by having to use their environment in a
different way in when they are to compete.
Answer:
$300
Explanation:
Given that s a health insurance program with co-payments of $10 per doctor visit.
Thus,
amount paid by insurance in 1 visit = $10
Amount paid by insurance in 6 visit = $10*6 = $60
Total bill charged by the doctor in 6 visit = 360
Amount paid by the consumer = Total bill charged by the doctor in 6 visit - Amount paid by consumer in 6 visit = $360 - $60 = $300
Since , consumer is the third party payer he pays $300 out of total $360 bill charged by the doctor.
In fraction ,portion of bill paid by the third party payer = 300/360 = 5/6
Thus, 5/6 portion of bill is paid by third party payer.
I would say that all four answers are correct. Trade and commerce between civilizations really did help to exchange new ideas, spread languages, share new inventions, and make some people rich.
Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.