The Titanic could stay afloat with four of its 16 watertight compartments flooded, more than anyone could imagine on a ship of its size. As the ice bumped along its starboard side, it punched holes in the ship's steel plates, flooding six compartments. In a little over two hours, the Titanic filled with water and sank Sep 25, 2008
Cost-reimbursable contracts involve payment to the supplier for direct and indirect actual costs and often include fees.
A cost-reimbursable contract is an agreement between two parties called the contractor and the owner. Here the contractor gets the reimbursement for the cost incurred while carrying out the work as per the contract, and also gets an additional fixed fee from the company or an owner.
Here the final pricing of the contract is determined later based on the underlying deal and the actual costs it took to complete a project given to the contractor.
Hence, cost-reimbursable contracts involve payment for direct and indirect actual costs.
To learn more about cost-reimbursable here:
brainly.com/question/23183570
#SPJ4
Answer:
<u>cost of goods manufactured schedule</u>
Raw Materials ($9,180 + $55,020 - $17,480) $46,720
Direct Labor $51,740
Manufacturing overheads :
indirect labor $6,510
factory insurance $4,700
machinery depreciation $4,380
machinery repairs $1,990
factory utilities $3,740
miscellaneous factory costs $1,980
Add Opening Work In Process $5,670
Less Closing Work In Process ($7,610)
Cost of goods manufactured $119,800
Explanation:
Cost of goods manufactured schedule shows a summary of results (cost) obtained from manufacturing activity during the production period.
Answer:
15%
Explanation:
The formula and the calculation of the price elasticity of supply are presented below:
Price elasticity of supply = (Percentage change in quantity supplied ÷ percentage change in price)
where,
Price elasticity of supply = 2
And, the percentage change in quantity supplied is 30%
So, the percentage change in price is
= 30% ÷ 2
= 15%
Answer: $5 per machine hour
Explanation:
Given the following :
Estimated manufacturing overhead cost = $550,000
Expected machine-hour to be incurred = 110,000
Actual manufacturing overhead = $575,000
Actual machine hour incurred = 120,000
The manufacturing overhead application rate:
Expected manufacturing overhead cost / Expected machine hour to be incurred
= $550,000 / 110,000 machine hour
= $5 per machine hour