First-line managers generally require more technical skills and fewer conceptual skills.
Conceptual skills are vital for top managers, less critical for mid-degree managers and no longer required for first-stage managers. As we move from the bottom of the managerial hierarchy to the pinnacle, the significance of these capabilities will upward thrust. Professional first-line managers can pay attention, talk, and write truely and continually, speaking for maximum effect with people at all degrees inside the organization, including team members, superiors, friends, and others. it is specifically important to correctly speak desires and expectations.technical abilities are the most vital for lower level managers because the managers surpervise the workers who produce products or serve clients. Group leaders and first-line managers want technical understanding and competencies to train new employees and help employees remedy problems. Pinnacle managers need sturdy conceptual abilities, whilst the ones at midlevels need top interpersonal abilities and those at lower stages want technical abilities. All managers want robust communication, selection-making, and time-management skills.
Because of this first-line managers need to be skillful hassle solvers who recognize the way to quick expand alternative plans and enforce them within teams. First-line managers have to remain agile and flexible when shifts unavoidably occur within an organizational structure.
Learn more about First-line manager here:-
brainly.com/question/14249035
#SPJ4
The name which is given to the process when a company maintains its price but removes or prices separately is known as E. unbundling
<h3>What is Price?</h3>
This refers to the attached value which is given to a good or service that is exchanged for that particular value.
Hence, we can see that when a company removes freebies such as free delivery or installation but maintains its price is known as unbundling and is a market activity.
Read more about marketing here:
brainly.com/question/25754149
Answer:
24.8 per hour
Explanation:
There are 3 workers and hence are three workstations. Consecutive activities are assigned to each workstation such that workload is as uniform as possible
Hence the time in each workstation (WS) is,
WS1 = 45+55+15 = 115 seconds
WS2 = 25+50+5+30 = 110 seconds
WS3 = 95+50 = 145 seconds
Workstation 3 has the highest processing time and hence is the bottleneck and determines the capacity of the process
Therefore capacity = 1/145 per second = 3600/145 per hour = 24.8 per hour
Answer:
The correct answer is letter "C": Cash, marketable securities, and receivables.
Explanation:
The quick assets of a company can easily be converted into cash. Quick assets include <em>cash, account receivables, </em>and<em> marketable securities</em>, which are equity and debt securities that can be converted into cash within one year. To calculate the company's quick assets add its cash, account receivables, and marketable securities and subtract its inventory from that result.
Answer:
Present Value= $18,181.82
Explanation:
Giving the following information:
Savings= $2,000
The machine will then begin to wear out so that the savings decline at a rate of 4 % per year forever.
Interest rate= 7%
To determine the present value of the savings, we need to use the perpetual annuity formula with the decline rate.
PV= Cf/ (i + g)
Cf= cash flow
PV= 2,000/ (0.07 + 0.04)
PV= $18,181.82