Answer:
Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
Answer:
Earth
Step-by-step explanation:
You don't need scientific notation.
The areas of similar figures are proportional to the square of their linear scale factor. If Mars is 1/2 the diameter of Earth, its total surface area is (1/2)² = 1/4 that of Earth.
That is, the land area of Mars is 25% of the total area of Earth.
The land area of Earth is 1-70% = 30% of the total area of Earth. 30% is more than 25%.
Earth has more land area than Mars.
Answer:
The Lowest Common Denominator is 30 9/10 = 27/30 5/6 = 25/30
53.778 is the answer. I hope this helps and have a good day!