Answer: The internal auditor discovered it when performing a routine audit of expense reimbursements
Explanation:
Marcus Lane, was a geologist who travelled all over North America and South America and this results in several expense reimbursements. Lane engaged in fraudulent activity by double booking his air travel.
He used cheaper ticket for the actual flight and more expensive ticket was returned for credit. But, he submitted the expensive ticket for reimbursement.
The fraud was discovered by the internal auditor while doing a routine audit of expense reimbursements. He was terminated and he agreed to pay the money back.
Answer:
$27,600
Explanation:
Amount transferred from the retained earnings account to paid-in capital accounts as a result of the stock dividend:
= Shares issued * Percentage of stock dividend * Market price
= 46,000 shares * 2% * $30
= 46000*0.02*$30
= $27,600
Based on the amounts that you are offered and their present values, the offer you should pick is Birr 10,000 in 12 years.
<h3>Which offer should you pick?</h3>
You should pick the offer with the highest present value.
Offer 1 present value:
= Birr 1,000
Offer 2 present value:
= 10,000 / (1 + 11%)²
= Birr 2,858
Offer 3 present value:
= 25,000 / (1 + 11%)³
= Birr 1,840
In conclusion, option 2 has the highest present value and so should be picked.
Find out more on present value calculations at brainly.com/question/27821989.
#SPJ1
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Group of answer choices.
A. the supply curve, resulting in a lower equilibrium price.
B. the supply curve, resulting in a higher equilibrium price.
C. the demand curve, as consumers try to economize because of the shortage.
D. the demand curve, resulting in a price ceiling in the market.
Answer:
B. the supply curve, resulting in a higher equilibrium price.
Explanation:
In this scenario, a severe freeze has damaged the Florida orange crop. Thus, the impact on the market for orange juice will be a leftward shift of the supply curve, resulting in a higher equilibrium price.
An equilibrium price can be defined as the price at which the quantity of goods demanded is equal to the quantity of goods supplied.
Additionally, the equilibrium price is generally said to be stable because at this price, the quantity of goods or services demanded is equal to the quantity of goods or services supplied to the consumers.