Answer:
0.3 feet
Step-by-step explanation:
2.75(0.8)^x
in which x is the number of bounces after the firts bouce
bouce 12 would mean x=11
2.75(0.8)^11 = 0.2
Answer:
Step-by-step explanation:
Add the like term
Here -10x , -3x are like terms
15 , 2 are like terms
Bring the like terms together.
-10x + 15 - 3x + 2 = -10x - 3x +15 +2
= -13x + 17
Answer:
correct option is B. 10%
Step-by-step explanation:
given data
assets A annualised volatility = 10%
assets B annualised volatility = 20%
solution
we both A and B assets are 10% and 20% respectively
and we know that to achieve smallest portfolio volatility
we need to invest completely in the asset which has least volatility
and volatility can not be less than the asset having least volatility
so here minimum volatility that can be achieved is = 10%
so correct option is B. 10%
Hey Giraffe111!
5280 ft= 1 mile
x ft= 3 mile
5280*3=15840 ft!
I hope this helps;)
Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path
Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :
Probability
Thus the probability that the project will be completed in 38 weeks is 0.34.