Answer:
A) Analogous Estimation
Explanation:
Analogous Estimation is the process of comparing past costs and expenses of projects to make estimations for the current projects. This is usually used when there is data limitation for accurate estimations on the current projects.
Parametric is where a unit rate is devised to calculate project costs comprising of several units.
Bottom up estimation deals with estimating smaller cost components and then using the sum of these components to make larger estimates.
Option D is based on rough estimates on the time and effort required for a project.
None of the other options thus take into account past work other than the analogous estimation technique.
Hope that helps.
Answer:
D
Explanation:
Profit is Maximize when MR = MC
since MR=40 - 0.5Q
and MC= 4
Therefore:
40-0.5Q = 4
-0.5Q = 4 - 40
-0.5Q= -36
divide through by -0.5
Q = 72
since Q = 72
from Q = 160 - 4p
72 = 160 - 4P
-4p = 72 - 160
-4P = -88
divide through by -4
P = 22
Answer:
This popular saying applied to an organizational environment, can refer to upset customers in the sense that if your customers make any complaints or complaints about your products and services, you, as a professional representing the company, must be well prepared and trained to deal with this adverse situation in a way that is not a "person who fights fire with fire and ends up with ashes", that is, you must be well prepared to respond to the customer's problem in a friendly, fast way and that brings solutions that do it. return, and not in a way where the customer feels that their complaint has not been resolved well and will not do business with the company again.