Answer: $17,000
Explanation:
Given that,
Budgeted beginning cash balance = $16,000
Budgeted cash receipts total = $188,000
Budgeted cash disbursements total = $187,000
Desired ending cash balance = $40,000
The excess (deficiency) of cash available over disbursements for June will be:
= Beginning cash balance + Cash receipts - Cash disbursements
= $16,000 + $188,000 - $187,000
= $17,000
Answer:
a. public relations
Explanation:
As the name suggest that public relations means the relations that should be made between the organization and the general public, local government, leader groups, etc. It would create a positive image for the public at large by communicating with the people so that they get to know about the company
Therefore according to the given situation, the option a is correct
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.