Answer:
Ramon will read 70 each night.
Step-by-step explanation:
25% of 280
REMEMBER: "Of" means to multiply
25% x 280
Convert the percent into a decimal
0.25 x 280 = 70
So Ramon will read 70 pages each night.
Hope this helps!!
Answer:
choice C
Step-by-step explanation:
the same input has 4 different outputs so its wrong
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Answer:
A is the answer
Step-by-step explanation:
Answer:
C
Step-by-step explanation:
They are both acute angles so the measurement cannot be above 90 degrees (right angle).
m<ADC is clearly smaller than m<AEC therefore m<AEC must be bigger than 28 degrees. C is the only option that fits