1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
DochEvi [55]
3 years ago
10

What do you think we would see if we looked at that same portion of the sky with an even more powerful telescope that is in spac

e?
Biology
1 answer:
trasher [3.6K]3 years ago
7 0

Answer:

hi

Explanation:

more objects and closer. We can also look at more distant points in space

You might be interested in
Help To Check This Also
FrozenT [24]
I think the first one is right !.... but the for the other one it's B .
4 0
2 years ago
What do you think would happen if there was more glucose (sugar) than available NAD+? Explain.
EleoNora [17]

Answer:

n people who have developed diabetes, glucose builds up in the blood, resulting in hyperglycemia. ... And, too much sugar in the bloodstream can cause other types of damage to body tissues, which can increase the risk of heart disease and stroke, kidney disease, vision problems, and nerve problems in people with diabetes.

Explanation:

8 0
3 years ago
A section of DNA encodes a gene for an enzyme involved in cellular metabolism. If a mutation event occurs that results in the de
Lady_Fox [76]

Answer:

The correct answer would be C. The protein synthesized will contain many erroneous amino acids since the loss of one base will shift the reading of the encoded base sequence.

Deletion mutation that does not occur in the multiple of three bases can results in frame-shift mutation.

It changes the reading frame of nucleotide in DNA. Thus, the reading frame of codons in mRNA would also change.

Consequently, the sequence of amino acids in a polypeptide chain would change or alter. Thus, a protein would contain many erroneous amino acids.

An example of the same is shown below in the image.

4 0
3 years ago
What is the estimated expected (mean) time for project completion?
il63 [147K]
The estimated expected (mean) time for project completion is 50 weeks, time management includes all the activities necessary to achieve the target date of delivery of the project. It includes the following activities: identification of activities, logical sequencing of activities, estimation of duration of activities, and preparation of the project schedule. For the preparation of the schedule we will see various methods such as resource leveling, simulation, and the critical chain method.
3 0
3 years ago
ANSWER ASAP FOR A COOKIE!!
gulaghasi [49]
C. aquifer: it’s a permeable rock that can contain or transmit ground water
3 0
3 years ago
Other questions:
  • On a vertical number line describe the position of the integer that represents 100 degrees C?
    11·1 answer
  • experimental evidence shows that the process of glycolysis is present and virtually identical in organisms from all three domain
    10·1 answer
  • Magma sometimes approaches or escapes onto earths surface, where does this magma form ?
    14·1 answer
  • What continents are involved in the ring of fire ?​
    5·1 answer
  • What are the three main components of the cytoskeleton? For each, a) name the filament, b) what proteins/structures comprise it,
    8·1 answer
  • The amount of ____ that a food contains is measured in calories.
    15·2 answers
  • Located at the top of the trachea, the _____ helps a person speak.
    12·1 answer
  • What are Schwann cells and their function?
    12·2 answers
  • What are all of the biotic and abiotic things that interact in a particular
    5·2 answers
  • How is sucrose moved in sink?
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!