Answer:
The equation would be 2,250 - 120<em>m</em>
Answer: the answer is 6.38
Step-by-step explanation: You have to divide 25.40/4 you can use base ten blocks or draw it out or just divide that is how i got the answer!
Answer:
Step-by-step explanation:
To solve using completing square, we need to write the equation as x2+3x=17.
The next step is to add a number such that the square can be completed. The number must be equal to (b/2a)^2, so here it will be (3/2)^2 = 9/4
The equation then becomes x2+3x+(9/4)=17+(9/4).
Solving it further will get you the final answer
Answer:
p(on schedule) ≈ 0.7755
Step-by-step explanation:
A suitable probability calculator can show you this answer.
_____
The z-values corresponding to the build time limits are ...
z = (37.5 -45)/6.75 ≈ -1.1111
z = (54 -45)/6.75 ≈ 1.3333
You can look these up in a suitable CDF table and find the difference between the values you find. That will be about ...
0.90879 -0.13326 = 0.77553
The probability assembly will stay on schedule is about 78%.