Answer:
c. short-run average total cost is typically above long-run average total cost
Explanation:
In the case when the average of the total cost of the short run should be compared with the average of the total cost of the long run for a given output level so this means that the average of the total cost of the short run should be more than the average of the total cost of the long run
Therefore as per the given situation, the option c is considered
Answer: Elasticity of luxury weekend hotel packages in las vegas is -1.432.
Explanation:
Price elasticity of demand measures the responsiveness of quantity demanded to a change in the price of the good.
Mid point method-





Elasticity of luxury weekend hotel packages in las vegas is -1.432.
Answer:
The correct answer is True.
Explanation:
At the end of a common agreement, there is no consequence for any of the parties, since it is their will to end the contract that they previously agreed to sign
Termination of the lease by the lessor.
The lessor may unilaterally terminate the lease under the conditions established by law, paying any compensation that may arise.
The law expressly establishes when and why the lease can be terminated by the lessor, and only in those cases can the contract be terminated without there being room for the payment of a penal clause or non-compliance, if any, since in those cases the law in particular established how and why to terminate the contract, and set the penalties to which there is room.
Answer: Elasticity of demand is 7.06
Explanation:
P1= $2,750
P2=$2,880
Q1=446,000
Q2=321,000




Elasticity = -0.76
Thus, elasticity of demand for laptops is 7.06. This means that laptops are highly price elastic as it is greater than 1.
Answer:
Instructions are listed below
Explanation:
Giving the following information:
The high-low method involves taking the highest level of activity and the lowest level of activity and comparing the total costs at each level.
Mountain has recorded the following for the past nine months:
January:
Number of Cavities= 375
Total cost= $5,300
February:
Number of Cavities 500
TC= 5,850
March
Number of Cavities 350
TC= 5,200
April
Number of Cavities 600
TC=6,250
May
Number of Cavities 325
TC= 5,150
June
Number of Cavities 475
TC= 5,700
July
Number of Cavities 525
TC= 6,100
August
Number of Cavities 575
TC= 6,300
September
Number of Cavities 450
TC= 5,550
A) Variable cost= (Highest activity cost - lowest activity cost) / (Highest activity units - lowest activity units)
Variable cost= (6300 - 5150) / (600 - 325)= 4.18 per unit
Fixed cost= HACost - (variable cost per unit * HAUnits)= 6300 - (4.18*600)= 3792
Fixed cost= LACost - (variable cost per unit* LAUnits)= 5150 - (4.18*325)= 3792
B) Q= 400
Total cost= 3792 + 4.18*400= $5464