Answer:
Total Costs $ 675,880
Explanation:
Costs EWIP
Ending work in process 5,400 units
Materials = 5,400* $ 7 = $ 37800
Conversion = 5400 * 40 % * $ 13= $ 28,080
We multiply the unit costs to the the equivalent units to get the costs of ending work in process.
Cost Units Completed
Units Completed 30,500
Materials = 30,500* $7= $ 213,500
Conversion = 30,500* $ 13 = $ 396500
Similarly we multiply the unit costs to the the completed units to get the costs.
Materials Conversion
EWIP $ 37800 $ 28,080
<u>Units Completed $ 213,500 $ 396500 </u>
<u>Total $ 251,300 $ 424 580 </u>
<u />
<u>Total </u>
Materials $215300
<u>Conversion $ 424580</u>
<u>Total Costs $ 675,880</u>
Now we add both costs to get the total costs which are equal to the given costs.