Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
X=0. Y=-2. There is only one x value for this question.
Answer:
a₁ = 1
r = 3
Step-by-step explanation:
Since it’s a geometric series then
a₁ = 1 ( because 1 is the first term of the series)
3/1 = 9/3 = 27/9 = 81/27 = 3 then r=3.
Step-by-step explanation:
Answer:
Step-by-step explanation:
a decimal
2/3 = 0.7
8/5 = 1.6
-5/2 = -2.5
7/4 = 1.8
9/2 = 4.5
-11/3 = -3.7
13/5 = 2.6
-7/4 = -1.8
Esto es solo un bosquejo del número, usando un gráfico, use 0.1 para una unidad en la recta numérica.
- ________________________________________________________ +
| | | | | | | | | | | | | | | | | | |
-5 -4 -3.7 -3 -2.5 -2 -1.8 -1 0 0.7 1 1.6 1.8 2 2.6 3 4 4.5 5