Answer:
NPV =$ 60,311.80
Explanation:
<em>The net present value (NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.</em>
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
0 1 2 3
Operating cash flow 136,000 136,000 136,000
Initial cost (274,000)
Working capital (61,000 ) 61,000
Salvage value <u> </u> <u> </u> <u> </u> 1<u>5000 </u>
Net cashflow <u> (335,000) 136,000 136,000 212,000.</u>
PV inflow= (136000)× (1.1)^(-1) + (136,000× (1.1)^(-2) + (112,000)× (1.1)^(-3)
= 395,311.80
NPV =395,311.80 -335,000
=$ 60,311.80
Answer:
1.5 cars
Explanation:
Three employees can produce a total of:
= 4 × 3
= 12 cars in an hour.
Five employees can produce a total of:
= 3 × 5
= 15 cars in an hour
So, the increase in total product of labor as I increase the labor from 3 to 5 employees:
= Total product when 5 employees are hired - Total products when 3 employees are hired
= 15 - 12
= 3 cars.
So, the marginal product of moving from 3 to 5 workers:
= 3 ÷ 2
= 1.5 cars