Answer:
$13,000
Explanation:
Given that
The stock of the firm = $36,000
Invested amount in account receivable = $13,000
Invested amount in equipment = $11,000
So by considering the above information, the amount included in the initial project for net working capital is the account receivable i.e current assets minus current liabilities and the account receivable is come under the current assets so the same is to be included
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
A finance reporting accountant prepares periodic financial statements required for external reporting. They collect and analyze financial data, ensuring that all reporting complies with SEC and GAAP reporting regulations and guidelines. They also prepare internal reports as required.
Explanation:
Please mark Brainliest!
Answer:
D. Kurt’s division is less risky than the other divisions.
Explanation:
Based on the information provided within the question it can be said that the most likely reason is that Kurt’s division is less risky than the other divisions. Just as the saying goes "the greater the risk, the greater the reward", the same goes for the opposite, the lower the risk that a division has to undertake the lower the percent for the required return.