Answer: 8 minimum work stations is what would be needed.
Step-by-step explanation:
The cycle time is computed as the operating time daily divided by the scheduled output.
It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.
Therefore,
If you need to produce 30units/hour.
The average cycle time is as follow:
The average cycle time is the average time between the completions of units.
60/30= 2 average cycle time
=16/2
=8
8 work stations is the minimum number that would be needed.
It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.
If i mean .913 then .91 but if u wrote it correctly then 900
Chuck travels at A) 30 mph
since chuck and dana travelled at the same amount of time (2 hours), dana travels at 26 mph, which is 4 mph less, and chuck travels at 30.
Answer:
Percentage loss of the number of trees is
.
Step-by-step explanation:
Given: After a storm,
trees out of
were left standing.
To find: What is the percentage loss of the number of trees?
Solution:
We have,
Total number of trees 
Number of trees left standing 
Therefore, loss of trees
We now that 



Hence, the percentage loss of the number of trees is
.
Answer:
y=180-63-63/2=27degree...in triangle mln
x=180-27-63=90....in triangle mon